TRANSPORTATION DEPT
Bolton & Menk, Inc.
207684
2022 Fairmont, New Ulm TH 14 and TH 15 Signal Opti
1049248
2022 Fairmont, New Ulm TH 14 and TH 15 Signal Optimization
Overall this coordination project should benefit the citizens of these 2 communities but time will tell if the district receives
complaints of any kind
Project Duration
Thu, 02/17/2022 - 00:00
Thu, 06/30/2022 - 00:00
Thu, 06/30/2022 - 00:00
Yes
{Empty}
Contract Amounts
$62417.69
$-2571.99
$59845.70
Yes
TH
No
{Empty}
Stromgren,Nicole Lee
Nicole.Stromgren@state.mn.us
Overall timely but they wanted to implement when discussion on FYA was sequencing was still being negotiated
Decent quality. Again, I think there was a big learning curve on ALL the preferences that MnDOT has for the way these retiming
projects should be done including doing over all other controller programming parameters that may have an affect on
coordination and bring them up to MnDOT standards.
Within agreed upon budget
good
Yes
{Empty}
4 - satisfied