TRANSPORTATION DEPT
Short Elliott Hendrickson, Inc
122622
Construction Oversight of US 63 Mississippi River
1025809
Construction Oversight of US 63 Mississippi River Bridge in the City of Red Wing

The contract was to provide construction inspection for a large project
Project Duration
Mon, 04/03/2017 - 00:00
Wed, 07/01/2020 - 00:00
Thu, 03/31/2022 - 00:00
Yes
{Empty}
Contract Amounts
$5250152.59
$749068.22
$5999220.81
Yes
state aid, th, bond
No
{Empty}
Anderson,Mark W
Mark.W.Anderson@state.mn.us
The timeliness was appropriate for the work
The quality of their work was excellent.
The cost was appropriate for the work
good
Yes
{Empty}
5 - very satisfied