Submission Number: 24282
Submission ID: 74746
Submission UUID: 10883a0e-9866-45bf-9281-1f1047727408

Created: Thu, 01/19/2023 - 18:10
Completed: Thu, 01/19/2023 - 18:10
Changed: Thu, 02/09/2023 - 14:47

Remote IP address: (unknown)
Submitted by: admin
Language: English

Is draft: No
Current page: webform_submission_import

Locked: Yes
Pollution Control Agency
Bay West LLC
200829
Former Lindert's Hardware
{Empty}
The contractor will oversee the installation of two additional monitoring wells. The contractor will sample a total of 8 monitoring wells on a quarterly basis for EBD, VOCs, GRO, and DRO.
Project Duration
Fri, 09/24/2021 - 00:00
Thu, 06/30/2022 - 00:00
Thu, 06/30/2022 - 00:00
Yes
{Empty}
Contract Amounts
$49605.52
{Empty}
$45023.99
Yes
STATE
No
{Empty}
ARTIE DWORAK
Artie.dworak@state.mn.us
Satisfied
Satisfied
Satisfied
Satisfied
Yes
{Empty}
4 - satisfied