TRANSPORTATION DEPT
Toltz, King, Duvall, Anderson and Associates, Inc.
147460
Replace Bridges 85814 and 85816
1027418W09
Delivery two Bridge Replacements for letting.
Project Duration
Fri, 09/14/2018 - 00:00
Thu, 08/20/2020 - 00:00
Sat, 11/28/2020 - 00:00
Yes
{Empty}
Contract Amounts
$621836.60
{Empty}
$621836.60
Yes
TH
No
{Empty}
Breyfogle,Aaron J
Aaron.Breyfogle@state.mn.us
Delivered Project Docs on time
No quality issues
Design cost finished well under budget.
good
Yes
{Empty}
5 - very satisfied