Commerce Dept
Carlson McCain, Inc.
205653
Brown County (Former Rich’s Amoco), Sleepy Eye, MN
{Empty}
Removal and disposal of abandoned underground gasoline storage tanks at a former gas station in Sleepy Eye, MN. This is a statutory obligation under Minnesota Statutes, chapter 115C.
Project Duration
Wed, 12/29/2021 - 00:00
Thu, 06/30/2022 - 00:00
Thu, 06/30/2022 - 00:00
Yes
{Empty}
Contract Amounts
$30013.34
{Empty}
$22843.68
Yes
Petrofund Abandoned Tank Removal Program
No
{Empty}
John Houck
John.houck@state.mn.us
The project was performed on time in accordance with the start and end dates specified in the Work Order Contract.
The Contractor, Carlson McCain, Inc., and selected tank removal and tank liquid/sludge disposal subcontractors conducted the project in an efficient and professional manner.
Contractor's costs were within amounts established in the Master Contract. Subcontractor work was subject to competitive bidding, and the costs were reasonable for the work performed.
Contractor's staff managed the tank removal project in a professional manner. Carlson McCain’s experience with abandoned tank removal projects enabled them to prepare in advance for unexpected issues that sometimes arise during these projects.
Yes
{Empty}
5 - very satisfied