TRANSPORTATION DEPT
Stonebrooke Engineering, Inc.
205417
Pipestone TH 30 ICE Study
1048576
The consultant was hired to explore intersection control options and provide an ICE report for the intersection of MN Hwy 30 and CR 15/8th Ave SW in Pipestone, MN. District staff were unavailable to perform the work required for the ICE report due to
the current program workload
Project Duration
Tue, 12/28/2021 - 00:00
Mon, 05/30/2022 - 00:00
Tue, 05/31/2022 - 00:00
Yes
{Empty}
Contract Amounts
$45949.80
{Empty}
$45949.80
Yes
TH
No
{Empty}
Weller,Derek Randall
Derek.Weller@state.mn.us
Deliverables were submitted on time.
Deliverables were of high quality
Tasks were completed under budget
GOOD
Yes
{Empty}
4 - satisfied