TRANSPORTATION DEPT
Moriarty Scheduling Services, LLC
193023
International Falls Critical Path Management Sched
1046573
Project 3608-48 TH 53 I-falls Reconstruction required the contractor to provide a CPM schedule, and updated schedules as the project progressed. MnDOT needed support in reviewing and responding to the contractor's proposed schedules.
Project Duration
Fri, 04/30/2021 - 00:00
Wed, 06/01/2022 - 00:00
Tue, 05/31/2022 - 00:00
Yes
{Empty}
Contract Amounts
$29676.80
{Empty}
$29676.80
Yes
TH
No
{Empty}
Tillman,Jeff
jeff.tillman@state.mn.us
Vendor resource always responded in a timely fashion.
Vendor resource knows CPM schedules like the back of their hand!
Within budget
good
Yes
{Empty}
5 - very satisfied