TRANSPORTATION DEPT
Stonebrooke Engineering, Inc.
164580
Design for Bituminous Mill and Overlay TH 58 TH19
1027417W07
Lack of District staff to deliver these two projects.
Project Duration
Fri, 08/09/2019 - 00:00
Sun, 03/27/2022 - 00:00
Thu, 03/31/2022 - 00:00
Yes
{Empty}
Contract Amounts
$987995.06
{Empty}
$987995.06
Yes
TH
No
{Empty}
Trogstad-Isaacson,Mark
Mark.Trogstad-Isaacson@state.mn.us
Stonebrooke did a good job of maintaining both projects in the scheduled project timelines
Stonebrooke did an excellent job of maintaining the overall quality of both project submittals.
Sub's (Bolton and Menke) cost estimate was short of needed hours, but Prime (Stonebrooke) made appropriate adjustments to the overall project budget to come in under project budget.
GOOD
Yes
{Empty}
5 - very satisfied