TRANSPORTATION DEPT
HDR Engineering, Inc.
141123
I-35W @ I-94: Downtown to Crosstown Strategic Enga
1029786
The purpose of this contract was to have strategic engagement during the 35W@94 project and engage in a new way with the community. The focus was on a benefits based approach separate from the construction impact communications.
Project Duration
Mon, 05/07/2018 - 00:00
Mon, 01/31/2022 - 00:00
Mon, 01/31/2022 - 00:00
Yes
{Empty}
Contract Amounts
$1631804.69
$19451.80
$1651256.49
Yes
th
No
{Empty}
Tag,Aaron E
Aaron.Tag@state.mn.us
Most things were done on time. Usually the MnDOT review was the hang-up in the timeline and the team did a good job of adjusting to the MnDOT needs.
The quality of the products and events were really good.
The project came in under budget and most tasks were done well and on budget. The webcam costs were high, but that was not really the contractors issue.
good
Yes
{Empty}
5 - very satisfied