TRANSPORTATION DEPT
WSB & Associates, Inc.
132621
Twin Ports Interchange Project Manager Assisstance
1025814W10
The Twin Ports Interchange Project was a fast-tracked project that required assistance in the large amount of meetings, meeting support, risk management, and overall coordination
Project Duration
Thu, 09/28/2017 - 00:00
Sat, 10/31/2020 - 00:00
Sat, 10/23/2021 - 00:00
Yes
{Empty}
Contract Amounts
$669727.76
$1354317.50
$2024045.26
No
th-bond
No
{Empty}
Krysiak,John C
John.Krysiak@state.mn.us
Due to the ever changing schedule described above regarding work packages, risk, etc the consultant adjusted very well to these
changes.
Quality was good, work was professional and the project knowledge was there.
The contractors cost was adjusted multiple times due to the ever transforming project needs. The project went from 1 work
package to 2 to 4 then back to 2 due to budget constraints. All contract amendments were justified.
good
Yes
{Empty}
4 - satisfied