TRANSPORTATION DEPT
Barr Engineering Co.
177280
Phase I Environmental Site Assessment and Phase II
1036999
Conduct Phase 1 and Phase 2 site investigations ahead of R/W acquisition and construction.
Project Duration
Wed, 05/27/2020 - 00:00
Sun, 05/15/2022 - 00:00
Fri, 12/31/2021 - 00:00
No
{Empty}
Contract Amounts
$99333.44
{Empty}
$99333.44
Yes
th
No
{Empty}
Ustipak,Kelsi Rae
Kelsi.Ustipak@state.mn.us
Contractor kept the project moving forward even during project management transition
Continue to produce consistent reports for CMMT state-wide.
Contractor labor exceeded cost estimate but project remained under total contracted amount
good
Yes
{Empty}
4 - satisfied