TRANSPORTATION DEPT
Widseth Smith Nolting & Associates Inc
120579
Design for Biwabik ADA and urban portion of T.H. 1
1026016
MnDOT district did not have staff or time to complete this complex project.
Project Duration
Tue, 02/07/2017 - 00:00
Fri, 08/31/2018 - 00:00
Sun, 10/31/2021 - 00:00
No
{Empty}
Contract Amounts
$488023.79
$569982.65
$1058006.44
Yes
th
No
{Empty}
Peritz,Alex Joseph
Alex.Peritz@state.mn.us
Due to plan quality issues the consultant didn't meet the deadlines and the project got pushed a fiscal year
Consultant had a hard time meeting MnDOT standards for layouts and plans. The District had to do a lot of oversight on this project. Consultant had to resubmit a 60% plan due to the amount of issues. Plan issues resulted in rather large change orders
in the field.
Costs were in line with other MnDOT consulted contracts
GOOD
No
{Empty}
2 - dissatisfied