TRANSPORTATION DEPT
Olson & Nesvold Engineers, P.S.C
192565
Bridge Approach Panel and Structural Design
1046535
Consultant was required to develop specialized details/plan sheets (approach panel/structural elements) that Design would not typically have solid knowledge on.
Project Duration
Fri, 04/23/2021 - 00:00
Thu, 06/30/2022 - 00:00
Fri, 12/31/2021 - 00:00
Yes
{Empty}
Contract Amounts
$99305.00
{Empty}
$99305.00
Yes
th
No
{Empty}
Chock,John Michael
John.Chock@state.mn.us
Contractor was straight forward with time needs but always took into account MnDOT's project deadlines. All deliverables were completed in a timely manner and prior to final deadlines.
Contractor was able to produce plan sheets that met MnDOT's standards.
The cost for this contract was comparable to past similar costs for this type of work
GOOD
Yes
{Empty}
3 - neutral