TRANSPORTATION DEPT
Houston Engineering, Inc.
164230
TH200 Reclaim Roy Lake to Zerkel
1034228
Our own internal design staff in D2 did not have the capacity to develop the plan
Project Duration
Tue, 08/06/2019 - 00:00
Fri, 12/09/2022 - 00:00
Sat, 12/11/2021 - 00:00
Yes
{Empty}
Contract Amounts
$99455.45
{Empty}
$99455.45
Yes
th
No
{Empty}
Upgren,Matthew
Matthew.Upgren@state.mn.us
Very timely. no issues with responses or action items
Contractor quality was the best there is. top tier professionalism and intelligence. very accommodating and helpful.
The best I've ever seen. We hired Houston under a direct select contract ($100K limit) and they came in under budget. Many staff
in our own office said it could not be done at that price. Houston proved them wrong and also delivered maximum customer
service in the process.
good
Yes
{Empty}
5 - very satisfied