TRANSPORTATION DEPT
Toltz, King, Duvall, Anderson and Associates, Inc.
175715
BAS and HVAC Mechanical and Electrical Engineering
1036664
The purpose of the contract was to provide preliminary plans to bid the project for HVAC / domestic hot water / furniture
construction
Project Duration
Wed, 04/22/2020 - 00:00
Wed, 06/30/2021 - 00:00
Sat, 03/27/2021 - 00:00
Yes
{Empty}
Contract Amounts
$95545.46
{Empty}
$95545.46
Yes
TH
No
{Empty}
Kufner,Wendy
Wendy.Kufner@state.mn.us
The Contractor was timely completing their work.
Quality was appropriate.
Cost was appropriate.
good
Yes
{Empty}
5 - very satisfied