TRANSPORTATION DEPT
CNA Consulting Engineers
137118
TH 55 Storm Water Tunnel Inspection and Design Pro
1029472
All on-site inspection and recommendation/resolution of any technical issues will be provided by the contractor. Written documentation of inspection activities and recommendations will be provided to the MnDOT Construction Engineer
concurrently with construction work.
Project Duration
Thu, 02/01/2018 - 00:00
Sat, 06/15/2019 - 00:00
Wed, 03/31/2021 - 00:00
Yes
{Empty}
Contract Amounts
$106023.22
{Empty}
$106023.22
Yes
th
No
{Empty}
Shekur,Hailu Shamra
Hailu.Shekur@state.mn.us
This contract time extended due to weather impact not because of contractor fault.
Very Good.
Reasonable.
good
Yes
{Empty}
4 - satisfied