TRANSPORTATION DEPT
Collins Engineers, Inc
137742
Statewide Specialized Hauling Vehicles (SHV) Load
1026813
Per a directive by the Governor of the State of Minnesota, responding to a recommendation by the National Transportation Safety Board, MnDOT is proceeding with analyses of every bridge on the local State Aid roadway system to verify design and load rating capacity. The bridges on the State Aid system number in the 10,000s, and the computations for load ratings can be quite lengthy, so consultant assistance in this effort is needed on a regular basis
Project Duration
Tue, 02/13/2018 - 00:00
Sat, 02/01/2020 - 00:00
Tue, 06/30/2020 - 00:00
Yes
{Empty}
Contract Amounts
$367189.30
{Empty}
$367189.30
Yes
partnership/federal
No
{Empty}
Dimaculangan,Moises
Moises.Dimaculangan@state.mn.us
Additional time was required for final submittal, but consultant took appropriate corrective actions to get the job done.
The contractor had issues with quality of first submittal, but with the guidance of MnDOT produce an acceptable final product in the end. For the rest of the remaining submittals, the work were accurate and complete.
Finished within budget. The contractor adhered to budget as specified in the contract/scope of work.
good
Yes
{Empty}
4 - satisfied