Submission Number: 21804
Submission ID: 72268
Submission UUID: 08dcde23-777f-48bb-9515-021d3aabd298

Created: Thu, 01/19/2023 - 18:10
Completed: Thu, 01/19/2023 - 18:10
Changed: Thu, 02/09/2023 - 14:42

Remote IP address: (unknown)
Submitted by: admin
Language: English

Is draft: No
Current page: webform_submission_import

Locked: Yes
Pollution Control Agency
Barr Engineering Co.
167139
Landfill Data Study
{Empty}
Barr will perform a analytical study of emerging contaminants at landfill in support of design work for Freeway Landfill.
Project Duration
Thu, 10/03/2019 - 00:00
Tue, 06/30/2020 - 00:00
Tue, 06/30/2020 - 00:00
Yes
{Empty}
Contract Amounts
$49947.26
$2933.11
$52880.37
Yes
State
No
{Empty}
Patrick Hanson
Pat.hanson@state.mn.us
Very satisfied. Barr completed all tasks on schedule.
Very satisfied. Barr was able to perform an analysis of emerging data from MPCA data base and perform the required modelling in a very professional manner.
Very satisfied. Cost were within the contract specification and reasonable for the amount of work they performed. One amendment was added for $2933.11 to allow Barr to perform an analysis of additional data that became available after the work order was issued.
Very satisfied. Cost were within the contract specification and reasonable for the amount of work they performed. One amendment was added for $2933.11 to allow Barr to perform an analysis of additional data that became available after the work order was issued.
Yes
{Empty}
5 - very satisfied