Pollution Control Agency
West Central Environmental Consultants
161700
3M Oakdale GAC Installation Oversight FY20
{Empty}
WCEC will coordinate and supervise the installation of granular activated carbon (GAC) systems. This includes the oversight of annual GAC installations at up to 300 residences in in the Lake Elmo, West Lakeland, Stillwater, Oakdale, and Afton areas. WCEC will document cases where occasional troubleshooting visits (service calls) and system repairs were required to be performed as needed, when requested by residents. Other activities could include minor plumbing adaptations as required. Summary reports of progress will be provided, and a database of systems installed will be maintained by WCEC.
Project Duration
Fri, 07/12/2019 - 00:00
Tue, 06/30/2020 - 00:00
Tue, 06/30/2020 - 00:00
Yes
{Empty}
Contract Amounts
$29988.24
{Empty}
$26054.80
Yes
State
No
{Empty}
Tim Lockrem
timothy.lockrem@state.mn.us
Very satisfied
Very satisfied
Very satisfied
Very satisfied. WCEC’s project manager did an excellent job of tracking the project. He was very good at communication during the project, and I could rely on him to get the job done in a timely manner with good quality results.
Yes
{Empty}
5 - very satisfied