TRANSPORTATION DEPT
Stonebrooke Engineering, Inc
158094
Pedestrian Crosswalk Policy Development Guidelines
1033236
a need was determined to have a set of guidelines for agencies to create a crosswalk policy. There was a need to have a consultant gather input and provide research to make use of previous studies and guidelines. A contract was needed to define the scope of work and the total cost of the project.
Project Duration
Wed, 05/22/2019 - 00:00
Sat, 02/29/2020 - 00:00
Sat, 02/29/2020 - 00:00
Yes
{Empty}
Contract Amounts
$58900.67
{Empty}
$58900.67
Yes
PARTNERSHIP/STATEAID
No
{Empty}
Sinclair,Deborah K
Debbie.Sinclair@state.mn.us
There was a period of time during the project where tasks weren't completed on the communicated timeline, but after some sidebar meetings things were quickly reset and brought back in line with a revised timeline.
the graphics and text quality were very good and the consultant did a good job of incorporating input from the technical panel members.
the cost seemed reasonable given the scope.
GOOD
Yes
{Empty}
4 - satisfied