Administration Dept
MOCA Systems, Inc.
50487
Owner's Program Manager- State Capitol Renovation
02CB0015
To augment staff for the purpose of addressing public, tenant, and building operators' concerns and needs for the renovation of the State Capitol.
Project Duration
Thu, 08/09/2012 - 00:00
Wed, 08/02/2017 - 00:00
Thu, 08/31/2017 - 00:00
Yes
{Empty}
Contract Amounts
$1196277.41
$46270
$1242547.41
Yes
Bond proceeds
No
Not Applicable. RFP was advertised in the State Register.
Gordon O. Christofferson
gordon.christofferson@state.mn.us
Excellent
Excellent
At final closeout $55,789.78 of the total contract amount will be returned to the state.
Final contract amount will be $1,186,757.63.
Excellent
Yes
None
5 - very satisfied