Administration Dept
AP Midwest
131910
Construct MSH Ph 2 - Preconstruction Services
55SR0024
Provide preconstruction services for MSH Phase 2. Services included preconstruction planning, scheduling, estimates, bidding, qualifications, and assembling GMP for project.
Project Duration
Mon, 07/03/2017 - 00:00
Fri, 12/31/2021 - 00:00
Sun, 10/01/2017 - 00:00
Yes
{Empty}
Contract Amounts
$124100
$0.00
$124100
Yes
Bonds
Yes
AP Midwest was one of several contractors proposing and competing for the role of a CMr for MSH project. AP Midwest was selected to do both MSH Phase 1 and 2.
gary krocak
gary.krocak@state.mn.us
Met schedule needs.
Developed a good approach to the project start.
Fair. The construction cost was of $ 59 M.
Fair and satisfactory. Provided services and information needed.
Yes
{Empty}
4 - satisfied