TRANSPORTATION DEPT
SRF Consulting Group, Inc
59742
RURAL INTERSECTION CONFLICT WARNING (RICWS)DESIGN
2665
A consultant was required as part of this project to take on design & construction oversight as MnDOT staffing resources are
limited.
Project Duration
Fri, 03/22/2013 - 00:00
Sun, 02/28/2016 - 00:00
Fri, 06/30/2017 - 00:00
Yes
{Empty}
Contract Amounts
$469986.88
$538851.45
$1008838.33
Yes
th
No
{Empty}
Kronzer,Michael
Michael.Kronzer@state.mn.us
While sometimes constrained by the construction contractor, the oversight contractor was able to closeout the majority of the
project within the contract timeline.
Contractor worked hard to ensure design & construction was conducted to a high quality standard. Contractor also pulled
together the necessary materials & documentation to close out a complex design build project.
Contractor was within budget.
Very Satisfied
Yes
{Empty}
5 - very satisfied