Corrections Dept
Inspec, Inc
123556
Study Power Plant Exterior Structure at MCF Fariba
{Empty}
Visible cracks started to develop on the exterior of a building at MCF Faribault. This study was necessary to determine the extent of the cracking, as well as potential fixes and their associated costs.
Project Duration
Mon, 05/01/2017 - 00:00
Sat, 07/01/2017 - 00:00
Sun, 06/04/2017 - 00:00
Yes
{Empty}
Contract Amounts
$2500
{Empty}
$2500
Yes
Agency
No
{Empty}
Benjamin Kitograd
Benjamin.Kitograd@state.mn.us
Consultant completed the project ahead of schedule
The quality of the report was very good
The cost was reasonable
Their overall performance was good
Yes
{Empty}
5 - very satisfied