TRANSPORTATION DEPT
Kimley-Horn and Associates, Inc
111492
BRIDGE REHABILITATION
04484W09
Design a plan-set for 4 bridge rehab over RR. Included crash struts, crossovers, ponds, guardrail, lighting and traffic control
Project Duration
Mon, 07/11/2016 - 00:00
Fri, 12/01/2017 - 00:00
Sun, 04/30/2017 - 00:00
Yes
{Empty}
Contract Amounts
$370660.22
$28442.70
$399102.92
Yes
th
No
{Empty}
Young,Matthew
matthew.young@state.mn.us
Deliverables were on time and emails were followed up in a timely manner.
Quality was a concern throughout. KH hadn't worked with D7 before. Many comments during plan reviews. Instituted a 95%
plan review which isn't typical. That said, they followed up on the comments appropriately.
I didn't initiate the contract so I can't speak about cost negotiations.
Satisfied
Yes
{Empty}
4 - satisfied