TRANSPORTATION DEPT
HDR Engineering, Inc.
46957
FINAL BD CAYUGA INTERCHANGE RECONSTRUCTION BRIDGE#
909
Bridge design and plan production on an extremely aggressive delivery schedule.
Project Duration
Fri, 05/04/2012 - 00:00
Thu, 02/28/2013 - 00:00
Sat, 11/03/2012 - 00:00
No
{Empty}
Contract Amounts
$644786.93
{Empty}
$644786.93
No
bond
No
{Empty}
Stenberg,Paul Michael
Paul.Stenberg@state.mn.us
Majority of deliverables were submitted late without communicating that more time was necessary
Plan quality was lacking throughout the project and was apparent during construction. This was partially due to the aggressive
timeline, but more so due to lack of staffing to complete the project on-time.
This took a fair amount of back and forth to satisfy the TTAA requirements.
fair
Yes
{Empty}
5 - very satisfied