TRANSPORTATION DEPT
Stonebrooke Engineering, Inc.
101316
DESIGN ADA PEDESTRIAN FACILITIES FOR PROJECT
1001161
The purpose of this contract was to design ADA compliant ramps for inclusion into MnDOT's project SP 2781-432 I-94. MnDOT
did not have available resources that could meet the project timeline.
Project Duration
Thu, 10/01/2015 - 00:00
Tue, 02/28/2017 - 00:00
Tue, 01/31/2017 - 00:00
Yes
{Empty}
Contract Amounts
$99733.76
{Empty}
$99733.76
Yes
TH
Yes
It was felt this contractor could produce the quality required for this project and deliver their portion of the plan on the project
timeline needed.
Rauchle,Ronald M
Ron.Rauchle@state.mn.us
The project was completed on time which helped enable the I-94 project to be delivered on time.
The contractor has much experience in this area of design and the plan development and plan quality were excellent!
The contractor's cost for this design effort was reasonable. The knowledge of this contractor enabled this project to be
completed in an efficient manner.
very satisfied
Yes
{Empty}
5 - very satisfied