TRANSPORTATION DEPT
Kimley-Horn and Associates, Inc.
111903
TH 71 AND TH 7 ROUNDABOUT
1002954
The purpose of the contract was to complete final design plans for a roundabout at the intersection of US 71 and MN7
Project Duration
Fri, 07/08/2016 - 00:00
Wed, 03/15/2017 - 00:00
Tue, 01/31/2017 - 00:00
Yes
{Empty}
Contract Amounts
$193053.00
{Empty}
$193053.00
Yes
TH
No
{Empty}
Spellman,Teal Marjorie
Teal.Spellman@state.mn.us
The contractor was late on some interim deliverable dates, but the overall project plan set was turned in on time
The quality was overall ok. As I stated in other areas of this evaluation, deliverables had to be revised many times in order to get
the quality of work we needed to turn our project in.
$193,042.37 which was under budget by $11 dollars.
GOOD
Yes
{Empty}
4 - satisfied