TRANSPORTATION DEPT
Wiss, Janney, Elstner Associates, Inc
61278
DEVELOP BEST PRACTICES FOR INSPECTION OF POST-TENS
2345
Investigate and develop best practices to repair grout voids in post-tensioned bridges.
Project Duration
Fri, 04/19/2013 - 00:00
Sat, 01/31/2015 - 00:00
Tue, 01/31/2017 - 00:00
No
{Empty}
Contract Amounts
$134807.32
{Empty}
$134807.32
Yes
TH
No
{Empty}
Sobczak,Lori Ann
Lori.Sobczak@state.mn.us
Field work was timely. A time extension was required for the final report, much of which can be attributed to the review time
added by MnDOT and the contractor's ability to respond once the schedule shifted.
High quality of field and reporting work
Proposed costs prior to contract execution were higher than MnDOT expected. However, once the scope of work was refined to
match the budget and the contract was executed, there were no budget issues.
Satisfied
Yes
{Empty}
4 - satisfied