TRANSPORTATION DEPT
Stantec Consulting Services Inc
65724
CAYUGA BRIDGE RE-DESIGN RETAINING WALLS UTILITIES
3989
Stantec was involved in the original design. Their efforts were needed to make plan changes that develop during construction.
They did a great job of reacting to our problems as those problems occurred
Project Duration
Fri, 07/19/2013 - 00:00
Tue, 06/30/2015 - 00:00
Fri, 11/11/2016 - 00:00
Yes
{Empty}
Contract Amounts
$98496.30
$74524.60
$173020.90
Yes
TH
No
{Empty}
Kordosky,Steven R
Steve.Kordosky@state.mn.us
exceptional
good
The costs per unit of labor were reasonable
good
Yes
{Empty}
5 - very satisfied