TRANSPORTATION DEPT
AECOM Technical Services, Inc.
82075
Final Design – Miller Creek Bridges 79021 & 79026
6055
This contract provided final bridge design services for two structures that carry TH 61 over Miller Creek in Wabasha County. It was necessary to procure a consultant for these services because MnDOT accelerated the letting date and the Bridge Office could not deliver the design on the accelerated timeframe
Project Duration
Fri, 08/08/2014 - 00:00
Tue, 06/30/2015 - 00:00
Tue, 06/30/2015 - 00:00
Yes
{Empty}
Contract Amounts
$199936.72
$0.0
$199936.72
Yes
Trunk Highway
No
na
Jessica Duncan
Jessica.duncan@state.mn.us
Early versions were on time, but incomplete.
Below average
Good – stayed within budget
Below average...QMP was completed late and required several resubmissions.
Personnel listed on original QMP and proposal were not performing or checking work on 60% set.
90% submittal did not contain calculations until requested.
30% and 60% beam designs did not follow MnDOT standards. 60% abutment drawings did not follow MnDOT standards. Errors in quantities, a few dimensions, WP references, bar lengths, etc. were still noted after the 95% review set. Contractor did work to eventually include comments and correct errors, but with much guidance from MnDOT.
No
None
2 - dissatisfied