Realized timeframe/schedule would be impacted, so two amendments were completed for time extensions, all deliverables completed within final schedule.
Contract Administration/Authorized Representative.
There were two amendments processed on this project. The amendments were a result of the reconstruction of the laboratory.
Regretfully, the laboratory should have notified the agency of the impending delays and communicated clearly that the project needed to be put on hold until that time they were up and running again. Repeatedly amending the contract and not being able to accomplish the tasks in the contracted time expended quite a bit of time and expense for MnDOT Contracting Staff and the UMN.