TRANSPORTATION DEPT
Parsons Brinckerhoff
79001
Design Build Contract Admin Manual
98875w33
The FHWA required MnDOT prepare a Contract Admin Manual for Design-Build, and MnDOT agrees it is beneficial and needed.
Project Duration
Fri, 05/30/2014 - 00:00
Wed, 12/31/2014 - 00:00
Wed, 12/31/2014 - 00:00
Yes
{Empty}
Contract Amounts
$173222.53
$0.0
$173222.53
Yes
TH
No
{Empty}
Peter Davich
Peter.a.davich@state.mn.us
The project ran somewhat longer than usual, although it was primarily for internal workload (both MnDOT and PB) reasons. The last edits did take longer than necessary to complete, but it was not a large problem.
The quality of the document is good and as described in our meetings.
The project was completed within budget.
This was a solid performance. The quality was as good or better than expected, although the schedule had some partially-excusable delays.
Yes
n/a
4 - satisfied