Submission Number: 16581
Submission ID: 67045
Submission UUID: 3729df62-44c4-4a4e-bc5a-7b16f05dd766

Created: Thu, 01/19/2023 - 18:10
Completed: Thu, 01/19/2023 - 18:10
Changed: Thu, 02/09/2023 - 14:58

Remote IP address: (unknown)
Submitted by: admin
Language: English

Is draft: No
Current page: webform_submission_import

Locked: Yes
TRANSPORTATION DEPT
STANTEC CONSULTING SERVICES INC.
71053
FINAL DESIGN PLAN DISTRICT WIDE CULVERT REPAIR
04486w02
FINAL DESIGN PLAN DISTRICT WIDE CULVERT REPAIR
Project Duration
Tue, 11/12/2013 - 00:00
Tue, 04/15/2014 - 00:00
Tue, 04/15/2014 - 00:00
Yes
{Empty}
Contract Amounts
$144598.26
$0.0
$133979.63
Yes
TH
No
{Empty}
Scott Morgan
scott.morgan@state.mn.us
The contractor was very timely.
The contractor was high quality.
The contractor’s cost was very good.
The contractor did a good quality job on schedule and on budget. They had expert resources available to provide appropriate guidance and did a good quality plan and specifications. They did not have to have their hands held, nor did they go overboard. They did a good job of good enough is good enough. I would hire them again. You should have them design your website and forms.
Yes
None
5 - very satisfied