TRANSPORTATION DEPT
HDR Engineering, Inc.
85083
Metro-wide ADA curb compliance & Reconstruction
04485w08
Design office did not have a design technician to be assigned. Final Design Plan Review required at least 4 weeks before submittal to CO.
Project Duration
Tue, 10/14/2014 - 00:00
Thu, 04/30/2015 - 00:00
Sat, 03/07/2015 - 00:00
Yes
{Empty}
Contract Amounts
$199817.70
$44721.75
$244539.45
Yes
State Funds
No
{Empty}
Monty Hamri
monty.hamri@state.mn.us
Very satisfied given the VERY tight schedule that we had to turn in the final plan.
Satisfied.
Satisfied.
Satisfied
Yes
None
4 - satisfied