TRANSPORTATION DEPT
University of Minnesota
38051
Cooperative Intersection Collision Avoidance Syste
98691
The purpose of this contract was to try and improve safety at 3 intersections with technology developed by the contractor. In order to do this MnDOT needed to enter into a contract with the contractor.
Project Duration
Mon, 06/27/2011 - 00:00
Mon, 06/30/2014 - 00:00
Sat, 01/31/2015 - 00:00
Yes
{Empty}
Contract Amounts
$352143.25
$-16729.16
$335414.09
Yes
TH
Yes
The CICAS was developed and deployed with 80% funding from the Federal Highway Administration. The project was completed through a cooperative agreement between MnDOT and FHWA which specified the University of Minnesota as the contractor for the system. The project was a logical extension of the Intersection Decision Support (IDS) project and the initial design, installation and activation of the CICAS-SSA systems was performed by the University of Minnesota.
Daniel Rowe
Daniel.rowe@state.mn.us
There were times when response time to maintenance issues was less than desirable.
Contractor did quality work
Cost was reasonable.
Contractor did quality work.
Yes
{Empty}
4 - satisfied