TRANSPORTATION DEPT
CTC, Inc.
54087
Review/Analysis of Signal Circuitry Plans for High
1161
MnDOT requests responses for the review of grade-crossing signal plans to ensure compliance with Minnesota statutes and rules, to determine appropriateness and adequacy of equipment installed by reviewing material invoices for each project, to ensure that installation is in compliance with the Minnesota Manual of Uniform Traffic Control Devices and to provide technical expertise and design for railroad and traffic system pre-emption. Review of signal plans is required by Minnesota Rule 8830.2125. Signal plan review requires extensive knowledge of railroad signal installation and engineering. No one in MnDOT has the requisite training to perform signal plan review.
Project Duration
Mon, 10/08/2012 - 00:00
Mon, 09/30/2013 - 00:00
Tue, 09/30/2014 - 00:00
Yes
{Empty}
Contract Amounts
$71559.88
$28295.30
$99855.18
Yes
TH
No
{Empty}
Paul DeLaRosa
paul.delarosa@state.mn.us
Work was completed within the allotted time frame
The quality of work was acceptable
Cost came within reason for the scope of work
Above Average
Yes
{Empty}
4 - satisfied