Submission information
Submission Number: 16334
Submission ID: 66798
Submission UUID: c769f49d-7a70-4de8-b557-328c43947ac3
Submission URI: /form/vendor-performance-evaluation
Created: Thu, 01/19/2023 - 18:10
Completed: Thu, 01/19/2023 - 18:10
Changed: Thu, 02/09/2023 - 14:56
Remote IP address: (unknown)
Submitted by: admin
Language: English
Is draft: No
Current page: webform_submission_import
Webform: Vendor Performance Evaluation
Locked: Yes
1) The railing quantity issue (each of the two railing items was 390 Linear Feet to high in the plan). This will be an approximately $20,283.90 (+ tax?) expense to the Department. The associated Supplemental Agreement has been approved by OCIC. The bridge design consultant (AECOM) and Bolton and Menk (and multiple MnDOT offices) should have caught this error.
2) There was an error in the plan cross sections and earthwork calculation that should have been caught. This issue is currently in a supplemental agreement and under contention since this change substantially increases the amount of embankment (borrow) need for the project. This error is also potentially in the $13,000 - $30,000 range with $13,000 being the actual increase based on contract values and $30,000 being the increase if the increased embankment has to be negotiated in price.
We don’t expect perfection in a plan, but these were two fairly obvious issues that really should’ve been caught during either the Contractor’s or MnDOT’s QC/QA process. For the next contract, a bigger emphasis will be placed on QC/QA.
Their traffic control plans weren’t prepared to the level of detail that we expect initially, but after some further discussions BMI made significant improvements before the plan was advertised. The district has certain preferences for how traffic control plans should look, and after working it out on this contract I don’t foresee any similar issues on future contracts. A supplemental contract was required to do additional signing revisions post-letting. However this contract wasn’t due to any failures on BMI’s part during project design, these changes are due to new information not available during project design.
There were some issues with the storm sewer design, which was based off of old records and dated surveys. MnDOT shares some responsibility for that, having provided some of the data in question and not raising it as a potential issue.