Submission Number: 16325
Submission ID: 66789
Submission UUID: b9a1e283-d149-4d4a-b5d2-44d4ab410b44

Created: Thu, 01/19/2023 - 18:10
Completed: Thu, 01/19/2023 - 18:10
Changed: Thu, 02/09/2023 - 14:56

Remote IP address: (unknown)
Submitted by: admin
Language: English

Is draft: No
Current page: webform_submission_import

Locked: Yes
TRANSPORTATION DEPT
University of Minnesota - Duluth
353954
Wetland Mitigation in Abandoned Borrow Areas
89261W252
The proposed project would allow continued monitoring, data analyses, and annual reports for the existing demonstration site wetlands for an additional three years, bringing the total monitoring period to five years (as required by standard permit conditions). The effect of established treatments on native plant percent cover, species richness and diversity will be the primary focus, with special attention to monitoring and control of invasive plant species. Additional vegetation monitoring plots will also be established on other mitigation sites within the U.S. Trunk Highway 53 reconstruction corridor to evaluate their progress.
Project Duration
Mon, 03/28/2011 - 00:00
Sun, 08/31/2014 - 00:00
Thu, 03/31/2016 - 00:00
Yes
{Empty}
Contract Amounts
$142023.00
$0.00
$142023.00
Yes
TH
No
{Empty}
Sarma Straumanis
Sarma.Straumanis@state.mn.us
GOOD
GOOD
Good value
Good
Yes
{Empty}
4 - satisfied