TRANSPORTATION DEPT
Widseth Smith Nolting and Associates, Inc. (WSN)
92528
Bridge Design Services & Development Special Provi
1000498
Final Design Service and special provision
Project Duration
Wed, 05/06/2015 - 00:00
Wed, 08/31/2016 - 00:00
Sat, 01/09/2016 - 00:00
Yes
{Empty}
Contract Amounts
$88666.29
$0.00
$88231.30
Yes
TH
No
{Empty}
Paul Stenberg
paul.stenberg@state.mn.us
Contractor met all plan turn-in timelines.
All work was satisfactory.
Contractor was within budgeted cost and produced a satisfactory plan set.
Contractor produced a satisfactory plan that met the staging requirements and timelines in order to meet the project letting date.
Yes
{Empty}
4 - satisfied