TRANSPORTATION DEPT
WSB and Associates, Inc.
87436
Bridge 62926 Pier Footing Re-Design
7113
Due to an incorrectly located utility, Pier 6 needed to be moved from its original location. This required a redesign of Piers 5-7 and beams for Spans 6 and 7 of bridge 62926 to accommodate the in place utility.
Project Duration
Mon, 01/12/2015 - 00:00
Mon, 11/30/2015 - 00:00
Mon, 11/30/2015 - 00:00
Yes
{Empty}
Contract Amounts
$52600.00
$15800.00
$68400.00
Yes
TH
No
{Empty}
Karl Johnson
karl.johnson@state.mn.us
After the design method was agreed upon, the contractor moved quickly.
After the design method was agreed upon, the quality was satisfactory.
Satisfactory – Additional money was required due to MnDOT disagreeing with original design method chosen by the contractor.
The communication with the contractor was substandard during portions of the project. The tight schedule of the contract was negatively affected by MnDOT and the consultant disagreeing over the design method. After the design method was finalized, the contract moved swiftly.
Yes
{Empty}
3 - neutral