TRANSPORTATION DEPT
Toltz, King, Duvall, Anderson & Associates, Inc. (
90077
Design of three State Projects in Kandiyohi County
7251
Assistance was needed on these projects due to extra design work needed to deliver other projects also scheduled for 2016 construction. The State’s staff was not able to deliver the required plans in time for letting and construction without assistance.
Project Duration
Tue, 03/17/2015 - 00:00
Sat, 02/27/2016 - 00:00
Sat, 02/27/2016 - 00:00
Yes
{Empty}
Contract Amounts
$150164.83
$12799.35
$162964.18
Yes
TH
No
{Empty}
Matthew Brua
Matthew.Brua@state.mn.us
Contractor was able to provide all deliverables on time or early.
The Contractor’s quality was as expected: a high level of quality.
The Contractor’s cost was as expected: came in under budget.
The performance of the Contractor was at a high level, as expected.
Yes
{Empty}
5 - very satisfied