Pollution Control Agency
Terracon
63179-15-12
PETROL REMEDIATION, FORMER MIDTOWN SERVICE STATION
{Empty}
complete investigation and construction work.
Project Duration
Mon, 07/07/2014 - 00:00
Tue, 06/30/2015 - 00:00
Tue, 06/30/2015 - 00:00
Yes
{Empty}
Contract Amounts
$72261.00
{Empty}
$72261.00
Yes
state
No
{Empty}
Lauralin Kania
lauralin.kania@state.mn.us
The contractor had good schedule maintenance. All invoices were submitted invoices on time and the project finished on time.
The contractor did a good job of adhering to program requirements: the deliverables received were of good quality, and the reports received were clear and complete.
The contractor had good budget management. Three change orders were needed to add additional scope of work requested by the MPCA. No amendments were needed to amend the budget
The contractor’s overall performance was excellent.
Yes
{Empty}
5 - very satisfied