Submission Number: 15769
Submission ID: 66233
Submission UUID: 8f381a2f-5a8a-4d51-995c-b6571d8c2d63

Created: Thu, 01/19/2023 - 18:10
Completed: Thu, 01/19/2023 - 18:10
Changed: Thu, 02/09/2023 - 14:56

Remote IP address: (unknown)
Submitted by: admin
Language: English

Is draft: No
Current page: webform_submission_import

Locked: Yes
TRANSPORTATION DEPT
City of Blue Earth
44874
TH 169 Reconstruction Final Design Plan – Blue Ear
783
TH 169 Reconstruction Final Design Plan – Blue Earth
Project Duration
Mon, 04/23/2012 - 00:00
Tue, 12/31/2013 - 00:00
Fri, 08/29/2014 - 00:00
Yes
{Empty}
Contract Amounts
$614873.00
$230070.00
$844943.00
Yes
TH
No
{Empty}
Brett Benzkofer
brett.benzkofer@state.mn.us
Contractor delivered as per the project schedule
Plan quality was good
Good cost management and communication with State PM
The contractor’s overall performance was very good. The contractor’s PM was excellent and communicated very well.
Yes
{Empty}
5 - very satisfied