Pollution Control Agency
MSA PROFESSIONAL SERVICES
63180-15-09
REMEDIATION, FORMER AMOCO, MARBLE MN - LEAK 18768
{Empty}
complete investigation work.
Project Duration
Fri, 08/29/2014 - 00:00
Tue, 06/30/2015 - 00:00
Tue, 06/30/2015 - 00:00
No
{Empty}
Contract Amounts
$10184.00
{Empty}
$10184.00
Yes
unknown
No
{Empty}
Larualin Kania
lauralin.kania@state.mn.us
The project did not finish on time due to a lack of bidders to complete work. Otherwise the contractor's schedule maintenance was satisfactory; all deliverables were received on time.
The contractor did a satisfactory job of adhering to program requirements. The reports received were clear and complete. Overall the contractor did a satisfactory job of accomplishing the contract goals.
The contractor had satisfactory budget management. No amendments or change orders were needed to amend the budget.
The contractor’s overall performance was satisfactory
Yes
{Empty}
3 - neutral