TRANSPORTATION DEPT
University of Minnesota
17161
Development of an Advanced Warning System for Frac
89261 WO 1
Phase 2 purpose is to implement the results of 89261 WO#144, and overall to extend current bridge health monitoring technologies so that they provide measures of structural health and advance warning of distress in fracture-critical steel bridges.
Project Duration
Fri, 09/24/2010 - 00:00
Fri, 03/30/2012 - 00:00
Mon, 03/31/2014 - 00:00
Yes
{Empty}
Contract Amounts
$67950.00
$4000.00
$71950.00
Yes
TH
No
{Empty}
Moises Dimaculangan
Moises.Dimaculangan@state.mn.us
The contractor performed the work identified in the contract/scope of work. The contractor produced an acceptable final product but was delivered behind schedule. Communication was lacking
The Contractor complied with the terms and conditions of the contract.
The Contractor’s invoices were accurate with appropriate backup documentation.
The contractor representative is courteous, cooperative. They are knowledgeable about the project and have the expertise to provide assistance as requested.
Yes
NONE
4 - satisfied