TRANSPORTATION DEPT
HDR Construction Control Corporation
3000089859
Construction Inspection & Contract Administration
96356
The Contract was for construction inspection and contract administration services for four Metro wide landscaping projects. This was necessary to document construction contractor compliance with contract plans & specifications, and to document contractor payments.
Project Duration
Mon, 04/05/2010 - 00:00
Tue, 04/30/2013 - 00:00
Tue, 04/30/2013 - 00:00
Yes
{Empty}
Contract Amounts
$87280.75
{Empty}
$87280.75
Yes
State funds
No
{Empty}
Andrew Eller
Andrew.Eller@state.mn.us(link sends email)
Good.
Good.
Appears normal.
Field personnel needed some coaching on application of the spec with regard to 1512 and 1904, but overall was willing to learn and did a good job applying learned knowledge of the spec. Some issues obtaining monthly reports from contractor, and keeping the contractor on task with the weeding for 1928-56, however, this contractor was more difficult to work with and required a greater than normal amount of attention in order to enforce the spec.
Yes
{Empty}
4 - satisfied