Submission Number: 27645
Submission ID: 114541
Submission UUID: c9856cb5-ccfe-4a2b-8c52-58822a47bdf3

Created: Thu, 01/23/2025 - 22:51
Completed: Thu, 01/23/2025 - 22:51
Changed: Fri, 01/24/2025 - 20:43

Remote IP address: (unknown)
Submitted by: eric.clanton
Language: English

Is draft: No

Locked: Yes
Agriculture Dept
Terracon Consultants
24465
Terracon Phase XX Spec & MW Install Oversight
RWA253112
The environmental contractor (Terracon Consultants, Inc.) was being tasked to: prepare to prepare the Bid Specifications packet for the Phase XX Corrective Actions, provide oversight of the installation of two groundwater monitoring well nests (one shallow, one deep monitoring well in each well nest); collect groundwater samples; collect soil samples, coordinate the disposal of investigation-derived wastes associated with the installation of monitoring wells, collect sampling location information using GIS technology, and reporting of the sampling results in association with monitoring environmental conditions associated with the former Kettle River Company - Creosote Plant Site in Sandstone, Minnesota.
Project Duration
Fri, 03/01/2024 - 00:00
Sun, 06/30/2024 - 00:00
Sun, 06/30/2024 - 00:00
Yes
{Empty}
Contract Amounts
$33768.11
{Empty}
$33768.11
Yes
State (MERLA)
Yes
Terracon has been and is involved in other investigations associated with the former Kettle River Company - Creosote Plant Site and has done an excellent job. Terracon is aware of the specific problems associated with this project and has a good working relationship with the various property owners involved on the project. Terracon is being selected to assure project continuity and high-quality work.
Eric Clanton
eric.clanton@state.mn.us
The contractor completed services in a timely matter.
The contractor provided excellent quality on the project.
The contractor's costs were fair and reasonable. The contractor did a good job using appropriate level
personnel to conduct tasks.
The contractor's overall performance was very good. Terracon did a good job adapting to changing field
conditions.
Yes
{Empty}
5 - very satisfied