Pollution Control Agency
WSP USA Environment and Infrastructure Inc
235592
John's Service
{Empty}
The contractor will sample four monitoring wells on a quarterly basis for VOCs, DRO, and GRO. The contractor will also conduct corrective action implementation planning and obtain a revised right-of-way (ROW) access agreement. The contractor will obtain a NPDES permit and will conduct a pre-bid meeting and contractor selection for the excavation corrective action.
Project Duration
Fri, 09/08/2023 - 00:00
Sun, 06/30/2024 - 00:00
Sun, 06/30/2024 - 00:00
Yes
{Empty}
Contract Amounts
$42660.48
$0
$42660.48
Yes
State
No
N/A
Artie Dworak
Artie.dworak@state.mn.us
Satisfied
Satisfied
Satisfied
Satisfied - The contractor was unable to perform the excavation corrective action at this time. This is not the fault of the contractor, as the MPCA legal department continues to work to obtain an access agreement with CP Rail.
Yes
N/A
4 - satisfied