Transportation Department
Professional Engineering Services, Ltd
210483
Materials Sampling and Testing and Environmental Compliance/Storm Water Prevention Plan Monitoring during Construction
1049354
This was a large grading project for which had a large environmental impact and green sheets being an important aspect and
multiple different regulatory agencies monitoring this. We as the department felt it was best to have a dedicated professional
administer this portion of the project. We really had no complaints from other agencies. Everything went much smoother than I
anticipated. So exceeded my expectations.
Project Duration
Mon, 04/18/2022 - 00:00
Sun, 06/30/2024 - 00:00
Mon, 09/30/2024 - 00:00
Yes
{Empty}
Contract Amounts
$532401.38
{Empty}
$532401.38
Yes
bond funds
No
{Empty}
Klasen,Michael P
Michael.Klasen@state.mn.us
Contractor produced all deliverables in a timely matter. If there was anything I requested of them, it was addressed immediately. I felt they really cared about this project.
Reports were completed thoroughly, accurately and timely.
The contractor came in under budget which was good but the department extended the contract and the only thing I would
recommend is when this happens, if they could remind the department that an amendment to the contract should be executed to extend their contract.
good
Yes
{Empty}
5 - very satisfied